The ACE-ALM exam has 100 questions and runs 2 hours.
Question 1
After heavy rain, six consecutive runway edge lights are dark while the other lights on the same series circuit remain at normal brightness. A calibrated true-RMS instrument confirms 6.6 A at the constant current regulator (CCR). Subsequent testing under lockout finds a marked drop in primary-to-earth insulation resistance compared with earlier tests made under comparable conditions. Which fault best explains this combination?
Show answer & explanation
Correct answer: C - Two primary-to-earth faults bypassing the affected section
Question 2
An inspection crew checks the lights in a section with 1,600 feet remaining on an 8,000-foot instrument runway. Viewed in the landing direction, the edge lights in that section show yellow and the centerline lights alternate red and white. How should these color observations be recorded?
Show answer & explanation
Correct answer: A - Both patterns are correct at this point on the runway.
Question 3
A five-step, 6.6 A constant current regulator is being checked against FAA AC 150/5345-10H. At Step 4, a suitable calibrated true-RMS instrument reads 5.24 A, with a maximum measurement error of 0.01 A. What should the technician do about this reading?
Show answer & explanation
Correct answer: D - Accept the reading as within the Step 4 current tolerance.
Question 4
Stores must issue an in-kind replacement for a failed isolation transformer on a 60 Hz airfield circuit. The approved ratings are 100 W, 20 A primary, and 6.6 A secondary. Which FAA transformer type matches all of these ratings?
Show answer & explanation
Correct answer: B - L-830-5
Question 5
Just after ATC clears a maintenance vehicle to cross an active runway, the runway entrance lights illuminate red. The vehicle is still stopped behind the holding position, and the driver cannot see any approaching traffic. What is the appropriate response?
Show answer & explanation
Correct answer: B - Remain stopped and ask ATC to resolve the conflicting indication.
Question 6
A connector identified as a hot spot is removed during a coordinated outage. Testing establishes a contact resistance of 0.75 ohm at its operating temperature. Before isolation, the CCR maintained 6.6 A RMS through the connector. Which estimate and interpretation fit its resistive heat loss during operation?
Show answer & explanation
Correct answer: A - About 33 W; normal loop current can coexist with damaging local heating.
Question 7
As part of an approved test of an L-880 four-unit PAPI, a technician activates the tilt switch in one light unit. All four units extinguish 20 seconds later while the incoming supply remains normal. How does this response compare with FAA AC 150/5345-28H?
Show answer & explanation
Correct answer: C - It meets the whole-system shutdown and time-delay requirements.
Question 8
An isolated, unbranched airfield control cable extends 1,600 m from the vault. Its verified pulse propagation velocity is 160 m per microsecond. A time-domain reflectometer records an abnormal reflection 4.5 microseconds after transmission; this is the round-trip time. Along the documented cable route, handholes A, B, and C are 250 m, 450 m, and 650 m from the vault. Where is the indicated discontinuity?
Show answer & explanation
Correct answer: D - About 360 m from the vault, between handholes A and B.
Question 9
A replacement sign assembly must tell a pilot that the aircraft is on Taxiway B and that Taxiway D is reached by turning left. Considering inscription and background colors, which pairing correctly distinguishes the location panel from the direction panel?
Show answer & explanation
Correct answer: A - Yellow B on black; black D and left arrow on yellow.
Question 10
Two of the six bolts securing an in-pavement light fail inspection. The other four bolts pass, the fixture remains properly seated, and the repair will not involve lifting it from its base. Under the phased-replacement guidance in FAA Engineering Brief 83A, what is the minimum hardware replacement needed?
Show answer & explanation
Correct answer: D - Replace the two rejected bolts in kind, with new two-part locking washer sets.